The Pattullo Bridge is living on borrowed time. TransLink has concluded it can't be seismically upgraded and should get only minimal repairs until a new bridge can be built.

Pattullo Bridge seismic work scrapped as ‘cost-prohibitive’

TransLink opts to minimize rehabilitation strategy on 80-year-old span, push for new bridge instead (WITH VIDEO)



TransLink is abandoning most of its plan to rehabilitate the 80-year-old Pattullo Bridge and will instead do minimal repairs in hopes a replacement bridge can be built as soon as possible.

It was to start a two-year $100-million upgrade next spring to replace the bridge deck and perform the first phase of seismic strengthening.

But TransLink officials have been warned the seismic portion now looks much more challenging, with a price tag that was set to soar, if it could be done at all.

“It’s cost-prohibitive,” TransLink infrastructure management and engineering vice-president Fred Cummings said Friday.

“We can’t continue to spend money because we don’t have a technical solution to extend the life of the bridge.”

TransLink will proceed to replace the bridge deck with a concrete one and shelve the multi-phase seismic work.

It will mean less short-term disruption for drivers.

Work is expected to take place over about five months next summer, instead of 18 months, and TransLink expects to keep two lanes open at all times, without any of the complete bridge closures previously forecast.

The bridge, which is 30 years past its 50-year design life, remains vulnerable to being knocked out of service by a moderate earthquake, river erosion or a ship collision.

How long the existing Pattullo can stay in service before it must be closed is uncertain.

“On the outside, probably 10 years,” Cummings estimated, adding it depends how rapidly the bridge deteriorates.

TransLink staff monitor it daily and conduct detailed weekly inspections.

He said it’s urgent to solve the question of how to pay for the Pattullo replacement as soon as possible.

The bridge replacement was one of the projects that would have immediately advanced had voters not rejected a 0.5 per cent sales tax increase to fund transportation in this year’s plebiscite.

But many observers expected the new bridge would get built regardless of the vote.

Tolls are expected to cover much of the region’s share of the $1-billion cost of the new Pattullo, with one-third each coming from the provincial and federal governments, but there’s still a $90 million expected shortfall in toll revenue over 10 years that must come from somewhere else.

TransLink officials say chopping the rehabilitation spending from $100 million down to $25 million means the other $75 million can be put towards the replacement project.

Even if the remaining funding is quickly found, the earliest a new bridge could be open is five years – after two years of design and procurement, and three years of construction.

The change in the Pattullo strategy was outlined in a presentation to the TransLink board, in its first open public meeting since promising to end its policy of making all decisions behind closed doors.

The Pattullo Bridge is living on borrowed time. TransLink has concluded it can’t be seismically upgraded and should get only minimal repairs until a new bridge can be built. Black Press file

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Comments are closed

Just Posted

Rugby practices to return to Lower Mainland fields this fall

B.C. Rugby announced its return to play plan July 7

Surrey officer-impersonation scam continues ‘almost daily’

Police reiterate warning that demands for Bitcoin in exchange for waived charges are fraudulent

Proposed Marine Drive zone aims to make use of small lots ‘more efficient’

CR-3A zone discussed during White Rock’s first virtual public information meeting

Surrey-area associations gear up for hockey restart

But it’s not yet clear when city-operated rinks and rec centres will reopen

South Surrey bottle-depot owner calls for decorum among customers

Heimin Lee said his Semiahmoo recycling facility has been ‘like a war zone’ since Easter

The pandemic is widening Canada’s workplace gender gap

Gender pay gap is incentivizing fathers to work while mothers watch children, a new B.C. study has found

Canadian policing organization calls for decriminalization of simple illicit drug possession

Canadian Association of Chiefs of Police want policing focus of opioid crisis to be replaced with a health one

Vancouver double homicide leads to arrest in Harrison Hot Springs Wednesday

VPD and RCMP tracked dumped vehicle connected to killings to Chilliwack

Indigenous leader Ed John pleads not guilty to historical sex charges

Ed John’s lawyer entered the plea by telephone on behalf of his client

Woman who talked to unconscious husband for 30 years gets solace from B.C. study

Ian Jordan suffered a head injury when he and another officer were on their way to a call in Victoria in September 1987

RCMP investigate threat against Indigenous totem poles on B.C.’s Sunshine Coast

Police describe the nature of the threat as ‘sensitive’

Thief steals bucket truck in Abbotsford while worker is 20 feet in air

Employee is able to jump to safety after suspect drives into pole

Investigation clears RCMP in incident where man fell from Langley overpass

‘Officers acted commendably and placed themselves at risk’ police watchdog report finds

Ex-Okanagan Mountie forfeits 20 days’ pay after sexual misconduct review

A former Vernon RCMP constable made sexual comments, grabbed genitals of male officer in two incidents 10 years ago

Most Read