Kinder Morgan hopes to have its Trans Mountain oil pipeline expansion project under construction by the end of 2016 if all federal approvals come on schedule.

Oil pipeline review proceeds amid uncertainty

Kinder Morgan makes final argument for Trans Mountain pipeline twinning before NEB despite

Kinder Morgan pressed ahead with its final argument for the Trans Mountain oil pipeline twinning before regulators Thursday, even though the project is now cloaked in uncertainty with a new federal Liberal government intent on reforming the review process.

Trans Mountain lawyer Shawn Denstedt argued the 150 draft conditions for the project can address all environmental concerns, and he stressed the strong economic benefits to Canada from getting world prices for Alberta oil.

“We cannot accept that our resources will be forever held hostage and sold at a discount,” Denstedt told the National Energy Board. “Real and important benefits for all Canadians should not be cast aside based on improbable risks.”

The company hopes the NEB will recommend approval by a May 20 decision deadline – following arguments by interveners in the new year – and the federal cabinet will give the $6.8-billion project the green light.

But Prime Minister Justin Trudeau, speaking Thursday in Vancouver, reiterated the need for changes to restore public trust and ensure such projects have social licence to proceed.

Kinder Morgan Canada president Ian Anderson said federal ministers have indicated projects like Trans Mountain that are already under review will continue and “not go back to any restart or square one review.”

But he said they’ve also been told there will be some sort of “transition treatment” for all projects, even those under review.

“We don’t know what that means yet,” Anderson said. “We don’t know what that will do to our process.”

The addition of a second pipeline would nearly triple Trans Mountain’s capacity to 890,000 barrels per day, increasing oil tanker traffic from five to 34 each month.

Anderson said shippers that have contracted to use the pipeline have not wavered from their firm commitments to 707,000 barrels per day of capacity. The rest is to be sold on the spot market.

If approvals are issued on schedule, he said, construction could begin by the end of 2016 and the twinning would be finished by mid-2019.

“It’s the most highly scrutinized pipeline project by the NEB in history,” Anderson added.

He said the project would bring major improvements to marine spill response capabilities along the shipping route from Vancouver past Sooke, with more than $100 million invested and 100 jobs created at five new bases.

Anderson stressed Trans Mountain’s 60-year history of operations and the fact the second pipeline largely follows the existing one or other brownfield corridors.

Next month, project opponents will respond.

The NEB will hear intervener oral arguments Jan. 19 in Burnaby. The City of Surrey will be the first intervener.

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

PHOTOS: One injured in shooting on South Surrey-Langley border

Shots reported near 194 Street and 34 Avenue, burned-out vehicle found in 18100-block of 12 Avenue

PHOTOS: South Surrey skunk family photo earns honourable mention in BC SPCA contest

Winners of society’s latest wildlife photography contest announced

Surrey wrestler Jason Bains receives four-year suspension for using banned substance

Queen Elizabeth Secondary grad tests positive for steroid Turinabol, silver national medal removed

COVID-19 exposures reported at four more Surrey schools

Fraser Health has created a new webpage listing COVID-19 cases in schools

UPDATED: COVID-19 outbreak declared at Peace Arch Hospital

Provincial health officer says outbreak is in the facility’s rehab unit

VIDEO: B.C. to launch mouth-rinse COVID-19 test for kids

Test involves swishing and gargling saline in mouth and no deep-nasal swab

Record-breaking 165 new COVID-19 cases diagnosed in B.C. in 24-hour period

Fifty-seven people are in hospital battling the novel coronavirus

B.C. teachers file Labour Relations Board application over COVID-19 classroom concerns

The application comes as B.C.’s second week of the new school year comes to a close

Young Canadians have curtailed vaping during pandemic, survey finds

The survey funded by Heart & Stroke also found the decrease in vaping frequency is most notable in British Columbia and Ontario

Report raises questions about COVID outbreak that killed 25 seniors at Langley Lodge

CEO defends leaked document that’s igniting queries about BC’s most deadly COVID outbreak

PHOTO: RCMP escort beaver across busy Chilliwack road

Motorists had to exercise patience as the slow-moving creature crossed several lanes of traffic

B.C.’s COVID-19 economic recovery plan: Top 5 things you need to know

Jobs training, tax incentives for employers to hire staff and more

March to protect old growth, stop industrial logging coming to B.C. Legislature

Organizers say they want to give frontline communities a bigger say in nearby logging

B.C. releases details of $1.5B economic recovery plan, $660M in business tax incentives

Economic plan includes support for employers, as well as training for workers

Most Read