Drone photo of Park Bridge completed in 2015 in Kicking Horse Canyon shows challenge of highway widening through the Rocky Mountains. (Ministry of Transportation)

Kicking Horse widening budget up $151 million as bidders invited

Union-only construction adds 5.8% to price of B.C.’s toughest project

B.C.’s transportation ministry is inviting bids to design and build the most difficult highway project in the province’s history, with costs going up, mainly due to union-only construction and engineering changes.

The latest cost estimate for the fourth phase of the Kicking Horse Canyon widening project is $601 million, a $151 million increase since the 2016 project budget. The ministry estimates that $35 million of that is to implement the NDP government’s “community benefits agreement” for public construction projects, requiring worker membership in approved building trades unions.

Other increased costs include additional geotechnical and other engineering work, additional foundation supports for bridges and retaining walls, consultation with Indigenous communities and a bigger contingency fund due to the risk and complexity of the project.

Phase four is four-laning of the final section of Kicking Horse Canyon east of Golden, 4.8 km from West Portal to Yoho Bridge. Construction is slated to begin in the summer of 2020, with completion by the winter of 2023-24.

The cost increase also includes an additional $23 million in interest charges, since the project was initially approved with a $450 million price tag in 2015.

Transportation Minister Claire Trevena emphasized the safety improvement needed in the Kicking Horse Canyon, which has an accident rate three times the average for B.C. highways and areas with effectively no shoulder for vehicles to pull off in an emergency.

RELATED: B.C. Highway 1 widening demanded for decades

RELATED: Single-bridge option chosen for Sicamous section

The average speed for the existing canyon road is 55-65 km/h, causing long backups behind transport trucks and recreational vehicles winding through the scenic route. The objective of the widening is to get the average speed up to 100 km/h as well as enhance safety.

The project will require closure of the Trans Canada Highway from Castle Junction to Golden for an estimated total of 15 weeks. A detour route using Highway 93 and 95 through Radium Hot Springs will add 104 km to the route, approximately an hour and a half of additional travel time.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

BC legislature

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Staff member at Surrey long-term care facility diagnosed with COVID-19

Fraser Health said a rapid response team is on site

White Rock’s namesake spray-painted black

Vandalism occurred sometime between Friday and Saturday

South Surrey resident blames city after house floods

Marilyn Molter said debris from city-planted maple trees easily clogs street drains

Sunny skies expected across Lower Mainland this week

After weeks of rain and smoke, Environment Canada forecasts clear skies and steady warm temperatures

Senior White Rock election worker not concerned about safety at the polls

‘Casting your vote will be like getting a take out coffee,’ says Elections BC CEO

QUIZ: Do you know what’s on TV?

Fall is normally the time when new television shows are released

Canadian ski resorts wrestle with pandemic-vs.-profit dilemma as COVID-19 persists

Few are actually restricting the total number of skiers they allow on the hill

Is it time to start thinking about greener ways to package cannabis?

Packaging suppliers are still figuring eco-friendly and affordable packaging options that fit the mandates of Cannabis Regulations

Victoria-area RCMP locate high-risk sex offender thanks to help of taxi cab driver

Scott Jones wanted on a Canada-wide warrant, ‘a risk to women and girls,’ police say

Join Black Press Media and Do Some Good

Pay it Forward program supports local businesses in their community giving

A (virtual) walk around the world by 88-year-old B.C. man

George Doi says it’s simple: ‘I like walking’

End of CERB means uncertainty for some, new system for others

As of a week ago, the CERB had paid out $79.3 billion to 8.8 million people

Horgan, Wilkinson trade barbs over MSP premiums, health care at campaign stops

Horgan called a snap election for Oct. 24 earlier this week

Most Read